The Faroese Appeals Board has confirmed the decision made by the environmental agency, Umhvørvisstovan, regarding Eysturlund’s application to build a 100-megawatt wind farm near Lambavík and to lay a high-voltage transmission cable between Lambavík and Fuglafjørður.
The board upheld the original decision, which denied the application, stating that current Faroese law requires a public tender process before any permit for energy production from wind power can be granted. Additionally, a separate permit is required for installing transmission cables. Because these legal conditions were not met, the agency’s decision to reject the application was confirmed.
The ruling emphasizes the legal framework for renewable energy projects in the Faroe Islands and the importance of following established procedures before construction can begin. It also signals that developers must carefully navigate regulatory requirements to move forward with wind energy initiatives.
Source: kvf.fo